Regulations Guide

Solar Canopy Regulations UK

Commercial solar canopy installations must comply with six regulatory frameworks: G98/G99 grid connection, MCS certification, Building Regulations Part A, CDM 2015, planning permission, and BS 7671 electrical installation. We manage every submission — you do not need to engage separately with any regulator.

Six regulatory frameworks for solar canopy installations

Each framework has a different authority, timeline, and compliance requirement. We handle all six as part of our standard full-service installation.

G98 (formerly G83) applies to solar systems below 50 kWp connected to the low-voltage (230V/400V) network. It requires notification to the DNO within 28 days of commissioning — not prior approval. G99 (formerly G59) applies to systems at or above 50 kWp, and to any system connected to the high-voltage network. G99 requires prior technical approval from the DNO — typically 8-12 weeks — before the system can be energised. For systems above 250 kWp, a multi-party G99 application involving the national grid may be required. We prepare and submit all G98/G99 documentation on day one of the design phase.

Key points
  • G98: notify within 28 days after commissioning
  • G99: apply before installation — 8-26 weeks
  • DNO may require protective relay settings review
  • G99 systems require a generation meter
  • We manage all DNO correspondence throughout

Regulatory timeline for a typical 200 kWp installation

Regulation When submitted Typical timeline Who submits
G99 grid connection Day 1 of design phase 8–16 weeks to approval Us (on your behalf)
Planning permission Week 2–4 of design phase 8–13 weeks to decision Us (on your behalf)
Building Regulations Before installation starts 2–4 weeks (building notice) Us + your structural engineer sign-off
CDM notification (if notifiable) Before construction phase 3 working days minimum notice to HSE Us as Principal Contractor
MCS commissioning At energisation Same day — 2–3 hours on site Our MCS-certified engineer
G99 commissioning notice Within 5 days of energisation Immediate (notification only) Us to DNO
SEG application After MCS certificate issued 2–4 weeks (supplier dependent) You, with our documentation pack

What you need to provide

We handle all of this

  • G99 grid connection application to DNO
  • Planning application preparation and submission
  • Building Regulations structural design and certification
  • CDM Principal Designer and Principal Contractor roles
  • MCS commissioning and certificate
  • Electrical Installation Certificate (BS 7671)
  • SEG documentation pack

What we need from you

  • · Half-hourly electricity meter data (12 months minimum)
  • · Site plan or aerial imagery of the car park
  • · Freehold or leasehold title confirmation
  • · Any existing S106 planning obligations or conditions
  • · Building drawings (existing, if available)
  • · Access confirmation for site survey
  • · Health and safety policy document

Full compliance included as standard

Every regulatory submission — G99, planning, building regs, CDM, MCS — is included in our full-service installation price. You do not engage separately with any regulator, authority, or DNO.

Get a fully compliant canopy design

Commercial Solar Across the UK

For rooftop and ground-mount projects, our hub site for UK commercial solar specialists.

Looking at the wider picture of solar car park installations.

Add charging infrastructure with commercial EV charging integration.

Compare PPA, asset finance, and capital purchase routes via commercial solar finance.

See current UK pricing benchmarks at commercial solar cost benchmarks.

For broader B2B context on commercial solar for businesses.

Quick numbers from our business solar calculator.

Current grant routes are tracked at UK solar grants for businesses.