Regulations Guide

Solar Canopy Regulations UK

Commercial solar canopy installations must comply with six regulatory frameworks: G98/G99 grid connection, MCS certification, Building Regulations Part A, CDM 2015, planning permission, and BS 7671 electrical installation. Each submission is normally made by the installer or the client's consultants.

Six regulatory frameworks for solar canopy installations

Each framework has a different authority, timeline, and compliance requirement. A full-service installer normally handles all six.

G98 (formerly G83) applies to small systems up to 16 A per phase connected to the low-voltage (230V/400V) network, and requires notification to the DNO within 28 days of commissioning — not prior approval. G99 (formerly G59) applies to larger systems above that limit, and to any system connected to the high-voltage network. G99 requires prior technical approval from the DNO — typically 8-12 weeks — before the system can be energised. For systems above 250 kWp, a multi-party G99 application involving the national grid may be required. Apply on day one of the design phase.

Key points
  • G98: notify within 28 days after commissioning (up to 16 A per phase)
  • G99: apply before installation — 8-26 weeks
  • DNO may require protective relay settings review
  • G99 systems require a generation meter

Regulatory timeline for a typical 200 kWp installation

Regulation When submitted Typical timeline Who submits
G99 grid connection Day 1 of design phase 8–16 weeks to approval The installer (on your behalf)
Planning permission Week 2–4 of design phase 8–13 weeks to decision The installer (on your behalf)
Building Regulations Before installation starts 2–4 weeks (building notice) The installer, with your structural engineer’s sign-off
CDM notification (if notifiable) Before construction phase 3 working days minimum notice to HSE The principal contractor
MCS commissioning At energisation Same day — 2–3 hours on site The MCS-certified installer
G99 commissioning notice Within 5 days of energisation Immediate (notification only) The installer, to the DNO
SEG application After MCS certificate issued 2–4 weeks (supplier dependent) You, with the installer’s documentation pack

What you need to provide

A full-service installer normally handles this

  • G99 grid connection application to DNO
  • Planning application preparation and submission
  • Building Regulations structural design and certification
  • CDM Principal Designer and Principal Contractor roles
  • MCS commissioning and certificate
  • Electrical Installation Certificate (BS 7671)
  • SEG documentation pack

What an installer will ask you for

  • · Half-hourly electricity meter data (12 months minimum)
  • · Site plan or aerial imagery of the car park
  • · Freehold or leasehold title confirmation
  • · Any existing S106 planning obligations or conditions
  • · Building drawings (existing, if available)
  • · Access confirmation for site survey
  • · Health and safety policy document

Ask for compliance to be priced in

Ask any installer to confirm that every regulatory submission — G99, planning, building regs, CDM, MCS — is included in the quoted price.

Get an instant estimate

Instant canopy estimate

Size and price your car park canopy in 30 seconds

Enter the number of parking spaces and your postcode and the page works out an indicative system size, capital cost range, annual generation and payback from the figures published on this site. It is an estimate, not a quote. Add your email afterwards if you want us to look at it with you; we reply by email.

Enter your spaces and postcode to see an indicative size, cost range, generation and payback.

Indicative only, not a quote. Assumes 1.7 kWp per space (see how the capacity is derived), £900–£1,400 per kWp installed (see the cost guide; the one published UK government illustration implies about £1,000 per kWp), PVGIS 5.3 yield for the nearest reference city, 24p/kWh for power used on site and 12p/kWh for export, and Annual Investment Allowance relief at the 25% main rate for a profitable company. Ground conditions, the grid connection, planning and EV charging are not included.

Why we ask: postcode sets the yield, spaces set the size, and timing tells us how to prioritise a reply.

How this works: this is an independent information site, not an installer. Your enquiry comes to us and we reply by email. We do not run a lead auction, pass your details to installers or add you to a marketing list.

Get your instant canopy estimate

Instant estimate · we reply by email